The NLP will automatically limit station run via Hydraulic (must be set) or Station limits (default 10) in the controller. To limit station run in a program, use a setting called Wait Completion. Wait Completion can be enabled for a single step or all steps and limits a program run to one or a select few stations to run simultaneously.
A step flagged for wait completion will prevent the program from running until all stations up to the flagged step have finished their runtime.
Run 1 Zone at a Time in a Program
- Navigate to → Irrigation Controller → Programs
- Click on the relevant program
- Select STEPS
- In the header, selectnext to Wait completion in the header
- You will see a √ on all steps. Stations will run 1 at a time.
Run >1 Zone Simultaneously
- Navigate to → Irrigation Controller → Programs
- Click on the relevant program
- Select STEPS
- Click on the step you want to
- Enable Wait completion by toggling to
- You will now see a √ on the step
- Repeat steps 1-6 to continue for additional steps.
In the example below, the program would run for 59 minutes:
- Station 1 - 10 minutes
- Station 2 - 30 minutes
- Stations 4, 6, 7 & 10 - 4 minutes
- Station 91 - 5 minutes
- Stations 1, 2, 3 & 4 - 10 minutes
To access a detailed explanation about Wait Completion, access the following link:
TN129 - Comparison of Step-Based Program Building - TWI to NLP
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article